Design/Construction Inspection for Five Dam Structures

Responsibilities

  • Design of Plans, Details, and Erosion Control Measures
  • Develop Specifications/Bid Documents
  • Post Design (including shop drawing/catalog cut reviews)
  • Permitting
  • Provide Construction Inspection Support to the County
  • Submit PS&E Documents
  • Address Deterioration and Erosion of Dam Structures
  • Prepare a Change of Plan for Atco Lake Dam to Stabilize Advanced Deterioration
  • Coordinate Lane Closures along Route 30 with New Jersey Department of Transportation

Owner

New Jersey Department of Public Works

Project Details

The project included the repair/rehabilitation of five dam structures in throughout Camden County to address comments received during the 2015 annual dam inspections, field reconnaissance, and collaboration with the New Jersey Department of Environmental Protection’s (NJDEP) Division of Dam Safety & Flood Control.

Project Uniqueness/Challenges 

  • Design, documentation, and engineers estimate was accelerated so the project could be advertised for construction two months after receiving Notice to Proceed.
  • Extensive coordination with NJDEP’s Dam Safety & Flood Control group was necessary in order to obtain “buy-in” and project.

Photos

 

We have been working with Keller Engineers of New Jersey and have found the firm to exhibit the highest quality of professional engineering in construction inspection/management. Keller has been exceptionally responsive, supportive, and versatile in all aspects of engineering, especially over the duration of construction inspection support by Keller on our recent New Jersey Turnpike projects. The staff is well trained and educated in the forefront of technology. Keller Engineers take both responsibility and pride in satisfying their customers of which we are grateful to be included. Robert J. Scancella, PE Vice President Construction Services KS Engineering, P.C