Pennsylvania Department of General Services, Huntingdon County
This project included the design and construction of a 71,000 gallon water storage tank and fire pump emergency generator control system to provide fire protection to the Department of General Services’ Huntingdon Readiness Center complex.
Project Uniqueness/Challenges:Â Due to the potential for standing water to freeze during the winter months, spray foam insulation was applied to the exterior of the tank following construction.
Keller Engineers has been the partnering Engineer firm for Bedford Joint Municipal Authority since 2009. Keller Engineers were a key component in every area from design to construction for the first phase of Shuster Way Heritage trail that was completed in 2015. Our partnership with Keller Engineers continued as we designed and completed the 2nd phase of the Shuster Way Heritage Trail in September of 2023. The staff are professional, passionate, and dedicated to a project from the beginning to completion. On behalf of Bedford Joint Municipal Authority, I would highly recommend Keller Engineers, Inc. Brian Sell, Chairman Bedford Joint Municipal Authority