Russo Building Demolition

Responsibilities

  • Survey
  • Permitting
  • Asbestos and Lead-based Paint Abatement Coordination
  • Preparation of Demolition Plan and Specifications
  • Bidding and Project Award
  • Construction Administration
  • Wage Rate Verification
  • Coordination with the County of Blair and City of Altoona

Owner

County of Blair, Blair County

Project Details

Keller Engineers was retained to provide engineering services necessary to demolish an abandoned facility and prepare the 2.1-acre site for future commercial development.  The project included an asbestos and lead-based paint report prepared by a sub-consultant. The structure had a concrete frame with concrete floor and roof framing. Concrete columns supported concrete beams and floor system.

Using an on-site mobile crushing operation, the concrete and brick materials from the building were used as fill.  The material was placed in the existing subgrade prior to the construction of a new facility.

Penn Cambria School District has collaborated the last 4 years with the Keller Engineer’s team to complete a multi-phased paving and drainage project on our HS campus. I have personally worked with Adam Long, Brian Smith and Shawn Ritchey throughout the entire project and they made Penn Cambria feel like we were their only client. The personal attention to our needs and specific details of this project were second to none. The communication aspect of the Keller Engineer Team was outstanding. We trust their process, their design and their commitment to a quality project that when completed, we are all very proud of. Bill Marshall, Superintendent Penn Cambria School District