West Providence Township Municipal Authority Wastewater

Responsibilities

  • Survey
  • Mapping Control
  • Grant and Funding Applications
  • Easement Right-of-Way Plans
  • Base Mapping
  • Courthouse Research
  • Utility Coordination
  • Wetlands Stakeout
  • Design of Wastewater Collection and Pumping Facilities
  • Act 537 Plans
  • Rate and Tap Fee Analysis
  • Infiltration/Inflow Analysis
  • Permitting
  • Bidding Services
  • Construction Inspection and Management

Owner

West Providence Township Municipal Authority

Project Details

The purpose of this project was to eliminate/reduce Inflow & Infiltration from the WPTMA’s collection system. The Authority and the Borough of Everett were under a corrective action plan from the Pennsylvania Department of Environmental Protection.

Contract 1 replaced approximately 8,000 LF of 8” of gravity sewer main, manhole replacement, lateral re-connections, related appurtenances and restoration.

Contract 2 replaced approximately 25,000 LF of 8” gravity sewer main, manhole replacement, lateral re-connections, related appurtenances and restoration.

Contract 3: replaced 3 pump stations.

A new collection system and 3 pump stations were built while maintaining operations of their existing systems.

Photos

Penn Cambria School District has collaborated the last 4 years with the Keller Engineer’s team to complete a multi-phased paving and drainage project on our HS campus. I have personally worked with Adam Long, Brian Smith and Shawn Ritchey throughout the entire project and they made Penn Cambria feel like we were their only client. The personal attention to our needs and specific details of this project were second to none. The communication aspect of the Keller Engineer Team was outstanding. We trust their process, their design and their commitment to a quality project that when completed, we are all very proud of. Bill Marshall, Superintendent Penn Cambria School District