Greendown Acres Mobile Home Park Wastewater System

Responsibilities

  • Survey
  • Mapping Control
  • Easement Right-of-Way Plans
  • Base Mapping
  • Courthouse Research
  • Utility Coordination
  • Wetlands Stakeout
  • Design of Wastewater Collection and Pumping Facilities
  • Replacing 96 mobile home laterals and reconnections
  • Infiltration/Inflow Analysis
  • Observation Ports
  • Permitting
  • Bidding Services
  • Construction Inspection and Management
  • Grant and Funding Applications

Owner

Blair Township Water and Sewer Authority, Blair County

Project Details

This project included the replacement of 2,800 LF of 8” PVC wastewater main, manholes, laterals, observation ports, and vents/cleanouts/traps; as well as the replacement of 96 mobile home laterals and reconnections, connection to existing wastewater system, related appurtenances and restoration. Keller Engineers’ team provided survey, design, bid process, and construction inspection/oversight.

Photos

Keller Engineers has been the partnering Engineer firm for Bedford Joint Municipal Authority since 2009. Keller Engineers were a key component in every area from design to construction for the first phase of Shuster Way Heritage trail that was completed in 2015. Our partnership with Keller Engineers continued as we designed and completed the 2nd phase of the Shuster Way Heritage Trail in September of 2023. The staff are professional, passionate, and dedicated to a project from the beginning to completion. On behalf of Bedford Joint Municipal Authority, I would highly recommend Keller Engineers, Inc. Brian Sell, Chairman Bedford Joint Municipal Authority

Contact Us Today!